What order to renovate a house UK | The Renovation Roadmap
The Renovation Roadmap

The order I'd renovate a house in, after doing some of mine in the wrong order

I'm over a year into renovating my first house with no building or property experience. I've learnt everything as I've gone, and made a lot of mistakes. Below are the 9 main stages of a renovation, in the right order, alongside why each one goes where it does + the mistakes I made along the way.

Project · House renovation
How to use this: the 9 stages below are the order in which I'd carry out my renovation if I knew at the start what I know now (and it's the order we carry out Aeterna Developments development projects in). Read through the whole document once first of all and start putting together a rough plan. After, find the stage you're at, check you've not missed anything & see what might be good to do next.
I had no experience when I started. This is what over a year of renovating my own house taught me & I keep updating it as I learn new things. Want me to tell you every time I update this roadmap?

Unsubscribe any time.

Where I mention tools or products, some links may be affiliate links & anything you buy through them supports me at no extra cost.
Every house is different, but this is the order I'd work to.
Tap any stage to jump to it.
Site diary · a confession

I viewed my house once before I bought it. I took a family member who'd bought & sold a few houses before, so I wasn't walking round with no clue on my own & I still got a full Level 3 survey done before going ahead. I don't regret only viewing it once.

But I'd recommend most people view a house at least twice, especially if it's your first. The second time round the excitement's worn off & you notice things you walked straight past & if you go at a different time of day or after proper rain you'll catch what the first viewing never showed you, like damp patches, what parking's like & how loud the street actually is.

1

Work out what you've actually bought

Everything after depends on it.
+
Check you've doneSurvey done & read properly · electrics, boiler & gas checked by pros · stopcock found & tested · damp looked for · asbestos tested if pre-2000 · rooms measured & filmed.

Why now: you can't make a proper plan until you know what's actually wrong with the house and what needs doing. The initial plan gets built around what you find, not the nice stuff like kitchens & paint colours. So get the right people out first: an electrician to check the electrics and maybe do an EICRElectrical Installation Condition Report. An electrician tests the whole installation & rates every fault. This report, not opinion, is what decides a rewire., a damp & timber surveyor if you spot anything of note or it smells musty & a structural engineer for any wall you're thinking of removing or any cracks you're worried about. For damp, use an independent surveyor who just sells reports, not damp proofing. A free survey from a company that injects walls for a living is basically a quote, not a survey.

The word survey gets thrown around a lot so it's worth clearing this up. Everything above is a specialist check for a specific worry. A house survey is the thing everyone should get. It comes in 3 levels, Level 1 is a quick once over for newer houses, Level 2 is the middle option for standard houses in a decent shape & Level 3 is a fuller breakdown. I'd always get Level 3 on anything old or in rough shape, but that's a personal preference. Mine was a Level 3 survey & it caught a few different problems in the house that I maybe wouldn't have previously been aware of.

Whilst organising your survey, it could also be good to look at your house's EPC online. It's free to view & it scores the house's insulation & heating, which is basically a preview of your future heating bills &/or any additional work you'll need to do to it to help retain heat.

Make sure you also get a Gas Safe engineer to check the boiler & gas pipework too and get their opinion on it, especially the longevity of it. Even though it may be more expensive in the short term, changing a boiler over whilst work is being done on the house may be better than the hassle of it years down the line when you're living there.

Check & consider
  • Survey done / booked in
  • EPC looked up
  • Electrics looked at by a professional
  • Boiler & gas checked
  • StopcockThe tap that shuts off all the water coming into the house, usually under the kitchen sink or where the mains pipe comes in. Find it before you need it in a hurry. found & tested
  • Damp looked for
  • Asbestos tested if pre-2000
  • Rooms measured & filmed
Skip this step and...you're planning around guesswork. The problems don't disappear, they just show up when you least expect it & it could start getting expensive to fix them out of order.
If the house was built or refurbished before 2000...assume textured coatings (Artex), old floor tiles, insulating boards, pipe lagging & soffits could contain asbestos until a test says otherwise. Don't sand, drill or rip out suspect stuff. Testing is cheap & some removals legally need licensed contractors.
Who does what
YouThe investigating (if you feel confident & competent)
A proThe checks & the decisions

Your job here is looking round the house, writing everything down & taking photos of it all. The actual decisions come from people qualified to make them, so an electrician for the electrics, a structural engineer for anything you're thinking of knocking through & a surveyor for damp. Once their answers come back you'll have a much better idea of what the next few stages look like for your house.

Site diary · a confession

I was stripping wallpaper in the living room & it led to me finding a cracked lintelThe beam that sits above a window or door & holds up the wall above it. If one cracks or gives way, the wall above it starts to drop. above the window. From the outside you could see the window was bowing. It was something that was even picked up on my Level 3 survey but I'd completely forgotten about it.

Go through your survey properly, look into anything it flags & get any fixes planned into your schedule of works from the start.

What I used
You can move on whenYou know what's actually wrong with the house & you've got answers back on anything you were worried about. If you're still guessing at any of it, you may need to do some more investigating.
2

Make it safe & dry

The inside can't start until this is sorted.
+
Check you've doneYou know whether water is getting in anywhere · gutters & downpipes cleared · no live leaks · decisions made on the windows & doors · old gas capped off, paperwork kept · dangerous electrics made safe.

Why now: the outside of the house is what protects everything you're about to spend money on inside it. So the roof, gutters, flashingsThe lead or metal strips sealing the joints of a roof, around the chimney & where roof meets wall. Where flashings fail, leaks start., soffitsThe boards tucked under the gutter overhang (the fascia is the one facing you). When they rot, water & birds get into the roof., anywhere causing leaks & any sources of damp all want sorting sooner rather than later.

The same goes for the windows & external doors. Changing them can make a mess of the reveals & the plaster round the openings, so if they go in after you've plastered you'll be patching up work you've already paid for.

Replacing windows is building regs work, so use a FENSAThe self-certification scheme for replacement windows & external doors (Certass is the other). The installer registers the job with the council & you get a certificate. No certificate = awkward questions when you sell. registered installer or go through building control & keep hold of the certificate, you'll get asked for it if you sell. Roof work can also fall under building regs depending on how much work needs doing.

That's the dry side of this stage. The safe side is anything that could hurt someone whilst the work is going on, so getting dangerous electrics made safe & any old gas appliances capped off properly. You'll have people in & out of the house from here on, so it wants doing before the work starts rather than part way through.

Check & consider
  • Loft checked, ideally after rain
  • Gutters & downpipes cleared properly
  • Roof checked by a roofer
  • Any roof work decided on
  • Any leaks found & stopped
  • Source of any damp found
  • Decisions about windows and doors made
  • Old gas capped off & certificated
  • Dangerous electrics made safe
Skip this step and...water gets into the new plaster, wiring, insulation & flooring, so you end up redoing work you've already paid for.
Once you start stripping the house back in stage 3, you may find additional problems. Get what's in front of you sorted now, but don't be surprised if more turns up. It's also why I'd consider making the decisions now but holding off on some of the big external spends (unless immediately needed and actively causing more problems) until stage 3 begins.
Who does what
YouThe decisions
A proThe information, then the work

The decisions at this stage are yours, not theirs. A roofer can tell you what the roof actually needs, an independent surveyor can tell you where damp is coming from & a window company can price the job, but whether you repair or replace it, or spend now or wait, is down to you & your budget. Get their answers in first, then decide, because a lot of what happens after this gets built around these calls.

Site diary · a confession

I never sorted my external doors at the start of the renovation and I now regret it. I've still got the same ones currently, I will be getting them replaced but when I do it'll mean patch up work and redecorating areas I've already worked on.

Make your decision early about windows and doors and get them sorted before the house starts getting put back together.

What I used
You can move on whenNothing is getting worse every day you leave it, so no major water coming in from anywhere, nothing is rotting & there's nothing left that you know needs doing urgently. The house is a safe place to be working in, so the electrics aren't dangerous & any old gas is capped off properly. And your decisions on the windows & doors are made, even if the work itself happens later.
3

Strip it back

Where most surprises are hiding.
+
Check you've doneDecided what's staying · suspect materials tested · services isolated before anything came out · everything not staying is out · what IS staying is protected · waste sorted.

Why now: everything hiding behind wallpaper, under carpets & inside boxed in corners changes your plan, so you want to find it now rather than after the trades have started & you're having to try reorganise everything last minute.

But before you start anything, you need to have decided what's staying & what's going. Not every renovation needs to go back to brick and some areas are fine to be saved. You also need to consider your circumstances. If you're living in the house from day 1 you don't want to rip everything apart and leave yourself with no toilet, nowhere to wash, nowhere to sleep, so from here on out it might need to be a room by room job.

A big rip out can be a lot more than just wallpaper. It's often better to start upstairs and work your way down. But I did the opposite due to upstairs being mainly cosmetic and downstairs being bigger works. My stairs also lead directly out my house so it meant I was never dragging anything dirty through any finished areas. When starting the actual work, it's important you know where stuff is connected and if it's structural. You can't just knock a wall down before you know if it's load bearing. You can't just remove an oven if it's still connected to the gas. If you don't know whether something is safe or not, the best thing to do is ask the professionals.

Waste is the part most people underestimate. I certainly did and regret it to this day. A skip fills quicker than you'd think & a house full of rubbish makes every other job slower. Figure out how you're gonna manage waste and stay on top of it, otherwise you'll be in a position like me where you're getting towards the end of the renovation and still have loads to get rid of. Keep in mind the cost of waste management too, because it all adds up. This includes access, if you can use skips or grab lorries on private land (e.g. put a skip or waste onto your driveway) this is often the most cost effective way forward. But if you don't have a front garden you may have to consider other avenues which may be more expensive, including roadside skips that require a permit from the council.

One way to earn some money back at the end of the rip out is to sell anything salvageable you don't want on eBay, Facebook Marketplace etc. I sold loads from leather chairs through to a TV, a washing machine and a tumble dryer. Also keep a hold of all your scrap metal, I did and it meant I was able to weigh it all in and get just under £200 back.

Check & consider
  • Decided on what's staying & what's going
  • Any suspect materials tested before work on / around them starts
  • Any structural changes checked by the professionals
  • Water, gas & electric isolated before work around these starts
  • Under & behind any potential problem areas checked
  • Anything being kept covered up & protected or moved to somewhere to store
  • Plan for waste sorted
  • Anything salvageable sold including scrap metal
Skip this step and...the surprises turn up one trade at a time instead of all at once. The electrician finds something, then the plasterer finds something else, and each one of those is another problem you've got to deal with.
Some of what you want to remove may be holding something up. Chimney breasts often carry the stack above them & the pot on the roof, some stud walls are doing more than dividing rooms, and joists notched for pipes or cables may already be weakened. If you're not sure what something is doing, get the investigations done before you touch anything.
Who does what
YouThe rip out (if you feel confident & competent)
A proAnything to do with asbestos containing materials, gas and electrics

This is the stage where doing it yourself can save a lot of money, so if you're going to get properly stuck in anywhere it's here. There are some things I didn't and wouldn't touch though. I had a full asbestos survey before commencing properly with the rip out and anything you think is suspect you should get tested. I also wouldn't go anywhere near any gas, electrics and major plumbing works.

Site diary · a confession

I had 2 leaks in the first 2 weeks of owning my house. One was from a faulty washing machine valve and the other was my fault because I didn't drain the old hot water tank before disconnecting the kitchen sink.

If you're to do anything like disconnect sinks, toilets, showers etc, be sure to fully understand how your water system works. In some houses, just turning off the stopcock and letting the tap run isn't enough.

What I used
You can move on whenYou've ripped out what needs to be ripped out based on your plans, and done the relevant work to protect things that're staying. You've uncovered most or all areas of potential concern so you know what you're dealing with as you move into stages 4 and 5.
4

Internal structure

The heavy work, whilst the house is open.
+
Check you've doneEngineer's calculations in writing · building control notified · party wall notice served if it applied · openings propped & beams in · no new cracks · completion certificate kept.

Why now: the heavy structural jobs happen whilst the house is already stripped back & before anything new starts. Everything after this builds on top of what gets decided and done here.

Before anything gets knocked through though, you need to know what's actually holding the house up. That's a structural engineer's job and it isn't expensive when comparing it to protecting the house you've just bought. I'd write a list of every wall you want gone & every opening you want made, then get an engineer to inspect everything at once. They'll check whether things are load bearing or not and if they are you'll be paying for calculations to be done for things like beam sizes to keep the house supported.

The majority of this work comes with waiting times. You have to wait for the structural engineer to do their calculations. Some structural work needs building control involved and depending on what work you might be doing and where sometimes things like the Party Wall Act may be needed. These things all take time, and if you're super organised then you may have already started the process for stage 4 whilst you're in stage 2 or 3 so you can get straight on with the works when you reach this stage.

If you're planning on adding additional insulation to the house then now is the time to be doing this, however some of it may also have to wait until after first fix work is done depending on the type of insulation and where it's going.

Check & consider
  • Every wall or opening you want changed listed
  • Structural engineer booked for one visit
  • Structural engineer has done calculations on the changes you want
  • Building control notified before relevant work starts
  • Party wall notice served two months ahead if a shared wall is involved
  • You know whether you're adding additional insulation and where
Skip this step and...you're guessing about what's holding the house up. Floors above can start to sag, cracks open up in rooms you never touched & doors stop closing properly. It doesn't always happen straight away either, so it can be months before you find out.
Who does what
YouThe decisions & taking out anything that isn't structural (if you feel confident & competent)
A proAnything structural

The house is yours and deciding what it should look like is your decision too. And once you've had a structural engineer do all the calculations, if something isn't load bearing you can do that job yourself if you want to. But anything structural is a different thing altogether. You need to follow the calculations and drawings to a tee, you need all the equipment like acro props to support the weight of the house whilst the work is being done and you need to move big heavy beams. It can be done yourself, but personally it's something I'd leave to the professionals who do it day in day out.

Site diary · a confession

From the moment I viewed my house I knew I wanted to take the wall between the kitchen and utility out and turn it into a single space. I didn't think it was load bearing and I had a structural engineer out who did the calculations and confirmed it wasn't.

This meant I was confident in being able to do the work myself, but that didn't stop me from being unbelievably nervous about doing it. But compare that to the structural lintel above the window in the living room. I left that to the professionals who had all the props and equipment needed.

What I used
  • Laser level
  • Spirit level
You can move on whenThe layout of the house is how you wanted, with any new structural support in as specified by the structural engineer. Doors still close & no new cracks have shown up in the days / weeks after the work. Building control have seen anything relevant and you've got the paperwork.
5

First fix: wires, pipes & heat

Before it starts getting put back together.
+
Check you've doneKitchen & bathroom layout settled · socket & light positions signed off by you · everything buried is in & tested · every wall & floor photographed before it got covered · notifiable work on a path to certificates.

Why now: cables, pipes & heating runs all live inside walls & under floors, so they go in whilst everything is open & before the house starts getting put back together again. Once a wall has been skimmed, adding a socket or moving a radiator means cutting it back open again.

Before any of it goes in though, you need to make more decisions. If a new kitchen or bathroom is coming, the layout has to be decided now, so appliance positions, hob type, where the shower, sink, toilet etc go because the pipes, cables and sockets all get done based on that layout. Don't forget to think about any flooring & carpets at this point too. You will also need to keep in mind that measurements may adjust slightly with plastering and any boarding that needs doing. The same decisions need to be made about each room. The house should work for you, so if you've planned your living room, bedrooms & maybe office, you'll know where you'll need sockets, switches, pipes for radiators etc. Think about where you'll spend your time in a room, if you'll want somewhere to charge your phone close to the bed, if you're putting a telly on a wall and want to hide the cables behind it, what appliances you'll have on your kitchen worktop. Every decision you make now is one you won't regret later. A good rule of thumb I learnt from an electrician is at least 1 double socket on each wall. I've got more than that on some walls but it's a good place to start. Go around and mark on the walls where you want all your sockets and switches and get all your quotes based on how you plan to live your life in each room. You'll also want to consider the types of sockets and switches you want as some are only compatible with certain back box depths.

This is also the stage where you think long term. Some costs like a full re-wire and a new boiler may be pretty expensive up front, but if you may have to get it done in a few years time anyway, and you've got to start drilling into a finished house, is it really worth waiting? And don't forget about everything to do with safety, smoke alarms, heat alarms, carbon monoxide alarms etc. I got my smoke and heat alarms wired in as part of my first fix and have a standalone carbon monoxide alarm.

A lot of this first fix work also needs sign off. Your electrician and plumber can typically give you the relevant certification though.

Check & consider
  • Kitchen & bathroom layout decided
  • Socket & switch positions marked up on the walls, light types decided on
  • Heating system decided on and location of things figured out e.g. radiators
  • Quotes agreed upon based on how you're planning the rooms to be
  • Smoke, heat & carbon monoxide alarms accounted for
  • Plan work for the first fixes to be done, plumbing normally goes before electrics
Skip this step and...you realise you're missing a socket or connection and are having to chaseCutting grooves into a finished wall to bury cables or pipes, then patching over the scar. Loud, dusty & avoidable if first fix happens before plastering. out walls you have already plastered and maybe even decorated.
Once the plaster goes on, nobody can see where any of it runs. Cables & pipes are supposed to sit in set zones, straight up or across from a socket or switch & along the tops of walls, but plenty of older houses have them running wherever suited whoever put them there. That is how people end up putting a screw through a live cable or a heating pipe years later. Photograph every wall & floor before anything gets covered, and use a detector before you drill into walls if you don't know what's hiding behind them.
People argue
Do you actually need a full rewire?

The internet typically says yes. The honest answer is work with your electrician & the EICR to come up with an answer. Things that point to yes: an old fuse box with rewirable fuses & no RCDs, black rubber or fabric covered cables, round pin sockets, scorch marks. Things that say it can wait: a modern consumer unit & a clean report.

What is true though, if your walls are already open, saying yes will never be less disruptive or cheaper than right now. Once the house starts getting put back together, that completely changes.

People argue
Does the boiler actually need replacing?

Work with your Gas Safe engineer on this one the same way you would the electrician on the re-wire. Things that point to yes: it's over about 10 years old, a repair quote is creeping towards half the price of a new one, or it's an old non condensing one burning far more gas than it needs to. Things that say it can wait: a condensing boiler that's serviced, working & not pushing past 10 years old.

What is true though, the system around it gets designed now either way. Pipe runs, radiator positions, combi or cylinder, all of that gets settled at first fix. If the walls & floors are open, moving the boiler or switching from a combi to a cylinder will never be easier than right now.

Who does what
YouPrep, labouring, planning the house (if you feel confident & competent)
A proElectrics & gas work

I took my own downstairs plasterboard ceilings down before first fixes started & my trades were able to work quicker because of it + it meant I was able to add in insulation after. Most prep and labour work can be done by you, just ask ahead what is wanted by those doing the work, but leave the main things to the professionals.

Site diary · a confession

The day my underfloor heating went down, I was mid rewire, so I had no power. The screedThe levelling layer poured over a floor, often with underfloor heating pipes buried in it. It has to dry fully before a floor covering goes on top & it dries slowly. was booked for the next morning & couldn't move, my plumbing second fixThe visible half of the job: sockets, switches & lights going live, radiators hung, taps & toilets connected, doors & trim fitted. By definition it happens after plastering. got dragged forward at the last minute & I finished the underfloor heating in the dark using my phone torch at the end of a very long day. It was one of the most stressful days of the whole reno & pretty much all of it came from not being fully clear on the order I need to do things.

Next time, before anything started I'd have an exact plan of action and list of when things need doing and what is dependent on it and make sure I give enough time between things to get them done.

You can move on whenEverything that will be covered during plastering is in and tested and it all matches the way you've designed and laid out the house. You've photographed all new runs of wiring and pipework so you know where it is for future reference.
6

Plaster & the wait

The most boring part.
+
Check you've doneEvery wall checked so you knew what needed doing · material types decided for the whole house · first fix finished, with anything the plasterer needed left out left out · walls dried to a uniform pale colour with no damp spots · woodwork on anywhere it needed to be.

Why now: the walls need finishing before any other stages can start. And everything after, kitchens, tiling, decorating, needs the flat, true surfaces this stage creates. If it's hidden by a unit, you may be able to leave parts open, but anything on show will need patching in and making right. Many people try DIYing plastering, and you can do it the proper way with a hawk, trowel, bonding and multi-finish or there's now systems out there like Dalapro Roll Nova but they're only really suitable for making existing walls flat. If I had one or 2 walls to do I'd have attempted plastering my house, but because I had to get practically my whole house done I left it to the pros.

Even if you're DIYing, if you don't know much about walls and plastering it's worth getting a plasterer in to come inspect the house so you know what needs doing and getting a quote from them just in case you decide you don't want to do it. Even though this is stage 6, the earlier you can do this, the better so you know what you're working with. But if you don't get someone in, you will want to go round wall by wall and give them a tap. Anything that sounds hollow or moves may need to be taken back to brick, but good walls (ones without a hollow sound) can usually just be skimmed overSkimming is the thin finishing coat of plaster that makes a wall glass-flat. Looks easy on video. It is a years-of-practice trade skill. if they need it. Some walls may need to be boarded to give a surface suitable to be skimmed and this is typically done by either dotting and dabbingSticking plasterboard to masonry on blobs of adhesive. Quick, and handy for hiding pipes or cables, but it leaves a void behind the board, so heavy fixings need to reach the brick & on a damp-prone wall moisture can sit in there out of sight. or screwing the boards into joists, depending on the type of wall. Another thing that will impact the types of materials you use is the construction of your house. Some older houses need lime plaster to be able to keep them breathing and not cause damp.

You've also got to decide on what boards you want to use. Bathrooms normally want at least moisture resistant boards and around things like baths and showers you're going to likely want something like tile backer board.

All the prep work like the boarding & bonding out and patching in is very important to getting that final flat surface you want when it comes to skimming.

I left the plastering to the pros but I did a lot of the prep work beforehand like SDSing off old plaster on areas that needed to go back to brick, bonding in some of the sockets that had been chased out & blue grittingRolling a gritty bonding agent onto smooth or non-porous surfaces so fresh plaster has something to grip. Skip it on the wrong surface & the skim can let go later. relevant surfaces (anything not boarded) ready for the plasterers to skim over. All of this was agreed with my plasterers beforehand though.

Once the plastering is finished, then comes the boring part, the wait. Plaster needs some level of heat and ventilation to dry, but you don't want to give it too much heat too quickly or it can crack. You need to wait until all the plaster has dried out before you can mist coatA watered-down first coat of emulsion that soaks into new plaster & seals it. Skip it & your proper coats can peel off in sheets. it, which can take a couple of weeks, but you must 100% wait until the entire wall is a uniform pale colour with no damp spots. Try to mist coat too early and you can cause cracks, blistering or flaking.

At this point you will also want to remeasure your kitchen & bathroom spaces to make sure everything still fits.

I'm putting this one here because there's nowhere else really for it to go. Once the plaster is dry it might be time to get your woodwork on, your skirting boards and your architravesThe trim framing a door. With skirting, it's the finish line where walls meet floors & openings & where mitred corners test your patience. etc. The problem with this stage is, the actual moment you do it depends on what flooring you're going with. If you're having a hard floor like LVTLuxury vinyl tile, a hard floor made of click or glue down planks that look like wood or stone. Thinner than laminate or engineered wood & usually warmer underfoot., you will want to hold off, lay the flooring first, and then the skirting covers the expansion gap the flooring needs. If you're having carpets, you're fine to push ahead as soon as the plaster is dry as carpets go up to the skirting not underneath it. I personally have LVT downstairs & carpets upstairs so I did some at this stage and some during stage 8 after my kitchen went in. If you don't fancy doing your own woodwork, it's a job for a carpenter.

Check & consider
  • Walls checked (by yourself or a professional) so you know everything that needs doing
  • Material type (boards, plaster etc) decided for around the house
  • All first fix work finished and you know what cables or pipes need to be left out (double check with your electrician or plumber if you don't know)
  • Prep work agreed with the plasterer if you're going to do it
  • You know when your woodwork is going on and it's done if necessary
Skip this step and...every surface stays as it is, so the paint, the tiling & the skirting all go on walls that aren't flat or true, and everything you fit after it sits wrong.
Plastering is a much harder skill than it looks. Getting a wall flat, true & smooth enough that a light doesn't show every wave in it takes years of practice. This is also the stage that decides what the finished house looks like, because the paint, the tiling & the skirting all sit on top of it. Do a bad job here & the fix is somebody taking it back off & doing it again, so be honest with yourself about which walls you're willing to have a go at.
Who does what
YouThe plastering prep, any tidy-up between coats, some plastering and woodwork (if you feel confident & competent)
A proThe plastering and woodwork if you feel it's not for you

Doing the basic, boring work & paying for the skilled labour is what I did when it came to plastering. But if you go down this route ask whoever is plastering what prep they want before you start any of it. Different plasterers have different ways of working and different ways to prep. Don't make them have to do what you've already done because you didn't do it right. When it came to the skirting boards and architraves, that was a job I took on myself.

Site diary · a confession

I attempted putting up plasterboard ceilings with my cousin and had one drop on my head. It's arguably one of the funniest parts of the renovation and I'm so glad I got it on camera.

But the lesson here is sometimes you bite off more than you can chew. Me and my cousin were attempting something we'd never done before on an evening after we'd both finished work with the plasterer coming back the following morning to carry on the work. We could've carried it on, but after a couple of boards were up we made the decision with my plasterer it would just be easier for him to get it boarded.

You can move on whenEvery wall & ceiling that's had plaster on has gone a uniform pale colour with no damp spots left anywhere. The woodwork is on anywhere it needs to be.
7

Decorate

The beginning of the end.
+
Check you've doneMist coat on before any filling & sanding · every hole filled, sanded & caulked, then re-mist coated · painted top down, ceilings then walls then woodwork · a bit of each colour kept back for the snagging.

Why now: dust before decoration, paint comes after every dusty and messy trade is pretty much finished. The stage goes in three parts though, and the order of them matters. The mist coat goes on first, then you find and fix what it shows you, then you get it painted.

Before any of that though, there are some decisions to make and it's more than just what colour. Colour is the obvious one, and when choosing put tester patches on the actual wall & look at it in different lights over multiple days to see whether you actually like it or not. Even better if you move it around the room too. You also have to consider the paint type. There's the finish to think about, which matters as much as the colour. A flat matt hides imperfections but can mark easier. Bathrooms and kitchens want something that can handle moisture in the air. There are specific paints for woodwork. So it's important to take your time to make the right decisions for the best finish in each room. Personally, I took the easy route and colour drenchedPainting the walls, ceiling & woodwork of a room in the same colour instead of a white ceiling & white trim. Less taping up, and it makes a small room feel bigger rather than boxed in. almost everywhere as I love the way it looks.

Once the decision making is underway, it's time to begin the mist coat. A mist coat is a watered down layer of emulsion paint applied to bare plaster. It helps seal the surface and stops the plaster sucking all the moisture out of your final paint finish which could cause it to peel or flake. I used a white contract matt mixed about 50/50 with water and used a paint sprayer for most of the work. Different people use different paint to water ratios, you just have to find what seems to work for you and your application method, because you can also just do the traditional rolling onto the surfaces. When painting it's typically best to start with the ceilings and then move onto the walls after.

After the mist coat has dried, you'll be able to see more imperfections in the walls and ceilings. Now is when you do all the boring prep work to make sure the final finish is good. Filling in holes, sanding areas down to make them flat, caulkingFlexible filler for the gaps where surfaces meet (door frame to wall, window board to wall & later skirting to wall). Paint over it & the joints look seamless. any joins etc. A raking lightLight skimmed across a surface almost flat to it, like a phone torch held against the wall at night. It throws a shadow off every bump & hollow you cannot see head on. is the quickest way to find them. Once all the prep work is done, it's then time to re-mist coat all of those areas. Take your time here, I hate this work but the more time you spend getting it right the happier you'll be with the final finish.

Then it's onto the actual painting. A good rule of thumb is start at the top and work your way down. Begin with ceilings, then do your walls and then onto your woodwork. I was fortunate, because I colour drenched everywhere it meant I was able to just do everything in 1 colour without having to worry about doing much taping up.

You typically want 2 coats of paint on each surface and each paint will tell you how much time you need to leave it to dry before you can apply a second coat. It's worth working out how much paint you need before you start too. A paint will typically tell you how many metres squared it'll cover, so if you work out your total wall area you should be able to figure out how much to order. It's always worth having a bit more than you need too for all the touch ups during the snagging in stage 9.

Check & consider
  • Paint colour decided after looking at it in the relevant room in multiple lights over multiple days
  • Paint type & finish decided room by room
  • Know whether you're colour drenching or what colours are going where
  • Quantity of paint you need worked out
  • Mist coat, prep work and any additional re-mist coat done before any proper painting starts
Skip the prep work and...you'll have a finished paint job you aren't happy with that you've gotta look at every day. The prep is boring but very worth it.
If you're painting over old paintwork rather than fresh plaster, don't dry sand it. Lead pigments started coming out of paint in the 1960s & were gone by the early 1980s, so anything you think is from then or before is worth testing, like on window sills. Dry sanding lead paint, or stripping it with a heat gun, is what spreads lead dust through the house and that's not something you want.
Who does what
YouNearly all of it (if you feel confident & competent)
A proIf you don't feel like doing the work you can get a painter and decorator

This is a stage most people can undertake, but it's also one where if it's done badly you'll know. The prep is what separates a good job from a bad one, and the prep takes time. It normally takes more than just 1 go over of each imperfection before it's looking right. I used both paint sprayers and paint brushes + rollers throughout my painting and decorating, you can use what you feel most comfortable with.

Site diary · a confession

When I stripped wallpaper from my landing ceiling I had to build a contraption made out of 2 ladders and 2 scaffolding boards. It was safe enough but it wobbled and I hated standing on it.

By the time I came to paint it, I realised I didn't want to build that contraption, so instead used a paint sprayer with an extension arm to reach the impossible to reach areas.

What I used
You can move on whenEvery wall & ceiling has had its mist coat, its prep, a re-mist coat over anywhere that got patched & 2 coats of the final finish paint on top.
8

Second fix: kitchen & bathroom

When it finally starts to come together.
+
Check you've doneLayouts settled back at stage 5 & remeasured after the plaster · floor & kitchen done in the right order for the type of floor · wet areas tanked before any tiling · plumber & electrician back to commission their work · gas work certificated.

Why now: the majority of the work is done and now it's time to start putting the house back together. The layouts of the important rooms should've already been settled back by stage 5 and you've already re-measured after plastering to make sure everything fits as it should. Now it's all about making sure you have everything lined up to make this section as smooth as possible.

A kitchen can go on top of glue-down floors but it's not best practice for them to go on top of floating floors. So the floor you're having matters for when it goes in.

I fitted my own floating LVT floor but I didn't fit my kitchen and left it to a pro. At the time I didn't feel like I had enough skills to get it right, but since then I have fitted a kitchen on an Aeterna Developments project and it came out very well. If you're going to fit your own kitchen the installation instructions are pretty simple to understand, it's just about making sure everything is right to the millimetre.

In the bathroom it's very important that any wet areas are sufficiently tankedTanking is waterproofing the shower & bath zones before tiling. Tiles & grout are not waterproof on their own, the membrane behind them is what stops next year's leak. and waterproofed. Your bath and/or shower tray should've already been fitted at the end of your first fix and now it's time for the rest of the bathroom to be fitted. I went for moisture resistant LVT and fitted that myself and also tiled all my bathroom walls myself and did a good amount of the siliconing but left the actual fitting to a bathroom fitter.

Around this time you will also have your plumber and electrician back to do their final bits of work. This is stuff like putting on sockets and switches, connecting up appliances and commissioning their work.

Check & consider
  • When your floor should go in based on what type it is
  • You have everything lined up including deliveries of materials, the trades you're using and when they're coming in etc
Skip the planning and...you're rushing last minute to try and move things around to work. Kitchens normally have a lead time of 3 to 4 weeks, a good fitter will normally be booked up for weeks or months in advance. It's important you plan when everything is happening early to make sure all your 2nd fixes run smoothly.
Who does what
YouThere's a lot you can do during 2nd fixes
A proThe electrics, gas and major plumbing works + anything else you don't feel confident with

Kitchen fitting, electrics & plumbing were 3 things I left to the professionals. Tiling I did myself including all the waterproofing and prep work beforehand. The tiling itself was the hardest skill of the whole reno. You can do lots in this section, but much of it is intricate work and the final finish really matters. Make sure you give stuff way more time than you think it needs.

Site diary · a confession

A gas pipe got damaged during my kitchen install & one wall unit came back off the wall & stayed off for months whilst that whole saga got sorted.

Even in the right order things can go wrong, no matter how close you are to the finish. Be ready for it and don't let it derail you, you've already achieved so much making it to this stage.

What I used
  • Net-a-kitchen (my kitchen, tell them Benje sent you)
  • Wren Kitchens (Aeterna Developments project kitchens)
  • Easy Bathrooms (part of my bathroom)
  • Drench (part of my bathroom)
  • Reginox (kitchen sink)
  • Allura Click Pro in Blond Timber by Forbo (living room & kitchen floor)
  • Allura Click Pro in Grigio Concrete by Forbo (bathroom floor)
  • BAL All In One Plus primer
  • Mapei shower waterproofing kit
  • Peru Grey tiles by tile.co.uk (bathroom tiles)
  • QEP manual tile cutter
  • Makita angle grinder
  • Bihui tile levelling system
You can move on whenEvery tap runs, every toilet flushes, every socket works, the kitchen doors line up & the worktops are level. Plus you've got all the relevant certificates for gas and electrics.
9

Final touches & snagging

The bit I hate.
+
Check you've doneSnagging list written down room by room, not kept in your head · who's fixing each one agreed with your trades · doors sorted before the carpets went down · carpets ordered with their lead time planned for · any cracks of concern measured & photographed.

Why now: almost everything is done and it's time for the final few bits that push you over the edge. There's 2 ways to play this, you could put carpets in and then do the touch ups or snagging, which means you may have to cover the carpets. Or you can do the touch ups and snagging then get the carpets laid. I personally got the carpets done as soon as possible because I was tired of walking on bare floorboards with my crocs on.

Let's imagine you start with snaggingThe end-of-job list of small defects & unfinished bits. Written down room by room, it gets done. Kept in your head, it doesn't. though. This is the point where you walk around every room and point out every imperfection. A good way to keep track of them is to put a small post it note on the wall as well as write a list of what each thing is. You'll also want to decide who's doing what at this point. I personally do most of my own snagging on my house but some things you may need a trade for, especially if you used them for the job in the first place e.g. a decorator. It's also important you discuss with your trades early about snagging so you can work out payment terms. Trying to get someone back for a couple of hours work when you've already paid them will be a nightmare.

If you're changing your doors you will likely want to do it before you get your carpets laid, but it would be a good idea to know the thickness of your underlay and carpet so you know how much clearance you need.

Carpets typically have lead times of 2-4 weeks depending on their manufacturing process, how much they hold in stock, when fitters have availability etc so it would be good if you had already planned this out alongside the rest of the planning in stage 5 and had a carpet measure done by the time you were at stage 6/7. If I wasn't having my whole upstairs & stairs carpeted, I might've considered having a go myself but this is something I just left to the pros.

Expect to find at least some cracks over the coming weeks too. Most of them are natural and nothing to worry about. If there's any of concern keep an eye on them, measure & photograph them, and discuss them with the relevant people like a structural engineer or a builder. Everything else not of note can just be properly fixed and patched up.

By the time you've done all of this work, across these 9 stages, the house will pretty much be finished. Congratulations, you've renovated a house!

Check & consider
  • Decided whether the carpets go in before or after the snagging
  • Snagging list written down room by room
  • Decided who's fixing each snag
  • Any cracks of concern measured, photographed & an eye being kept on them
Get the carpets in early and...every job you've still got left walks its mess straight onto them, so you'll be covering them up & working around them for the rest of it.
Who does what
YouMost things at this stage could be done by you (if you feel confident & competent)
A proAnything you don't feel confident in doing

A lot of this stage could be done by yourself if you want to. If you've already got stuck in throughout the rest of the renovation, you may be feeling relatively confident in your skills and ability to pick things up. I certainly am a lot more confident than I was when I first started, but there's still some things like the carpets I left alone.

What I used
  • Rodeo Drive carpets in cream by Tapi
  • Brushed bronze sockets by Corston
  • Brushed bronze switches by Corston
You can move on whenYou're happy with how the house is looking and everything on the snag list has been ticked off.

You're further along than you think.

If you're stressing about doing things in the right order, you're already ahead of where I was when I started. Here's what I'd do next after reading this in full:

Save this somewhere you can easily access it, I'll also be updating it as I learn more and work on more projects.

Write a rough plan based on the stage you're at, make sure it includes all the important times you need to have decisions made or measurements for like kitchen, bathroom, flooring etc.

Find the specific stage you're at & go through it to check you've not missed anything important. If you're starting somewhere in the middle, it may also be good to check 1 or 2 stages before and 1 or 2 stages after too.

Keep showing up and keep moving forward, use this roadmap as a guidance but not a list of exactly what to do. Each house is different and each situation is different. If you feel like you're stuck or struggling, ask for help where you can even if that means sending me a quick message!

I had 2 leaks in the first 2 weeks of owning my house, knocked down a wall, dug 30 tonnes of concrete floor out by hand, fell through floorboards whilst painting and made so many mistakes along the way. My house is fine and yours will be too. I've gone from never having really used a drill before to creating this roadmap and being the co-founder of a property development company, Aeterna Developments. A willingness to learn and try, but also to know when it's not something for you to do, will set you up for success when it comes to renovating.

All the best, and feel free to reach out at any point with any thoughts, comments, questions or improvements for the roadmap.

Stay updated

I'll keep updating this as I learn more & work on more projects. Want telling when I do?

Unsubscribe any time.

This is my experience renovating my own house, not building advice. Only carry out any work if you feel confident and competent. Use registered professionals where necessary and when it's the law. In a listed building or conservation area, different rules may apply, so check with your council before any of this.

Every house and every situation is different, so nothing here is advice about yours, and rules and best practice change over time. You're responsible for the decisions you make about your own property, for any work you choose to carry out and for meeting building regulations and anything else that applies to it. I can't take responsibility for loss or damage arising from decisions made off the back of this page.